September 2018


Everyone is flat out working 

A lot of prep work went into the flat roof.  The waterproof under lay had to be put down




Different elevations had to be built in so that the water runs off at an angle




The flat roof wraps around the old house and the new extensions



The rubber roof is being laid




Finished flat roof




Battons being put on the flat wall (this is where the timber frame will be)








Brian is a gifted furniture designer (just in case you didn't know!)

Brian and Andrew are making all the woodwork for the house
He has made the window frames and is now spraying them
He chose Accoya timber, its a timber modified  in which a process called acetylation, a cutting-edge patented technology, enables it to resist rot,  defy the elements and stay strong for decades. Its guaranteed for 50 years above ground




Finished grey coat





Brian and Andrew put the finished frames into the window openings ready for plastering







All cavities were blocked up with cavity blockers in readiness for insulation pumping


Danny is back and working hard as always


The Stud wall and opening for the sitting room are going in.  This is going to be a sliding door.



Our Roofer is finishing the slate work





THE PLASTERS ARRIVED AND ARE FLAT OUT
They hid from the camera!!!