Week 16 ending 1/6/18
Week 17 ending 8/6/18We had a heatwave, up to 30 degree C on the roof!!
2nd June early morning
4th June, 30 degrees at 12.30 pm, the guys are starting to melt!!
6th June - still boiling
The guys eventually had to into the house and start some inside work
The weather broke (unfortunately) on Friday, 8th June, we are back to Irish weather now!! All the sun burned red-heads in the vicinity are happy again :)
Week 18/19
Week 18 w/e 15/6/18
Lots of framework going on upstairs for the bedrooms, bathrooms and walk in wardrobes
And our first lot of windows going in before we start slating the roof
Danny's bedroom
Charlotte's bedroom
View from the back
Lots of Frame work going on inside
Sitting Room with door into the kitchen
Bedroom with walk in wardrobes
Window Cills are going in